Project 245-20 Lorain County, OH Great Lakes has completed the Ohio Turnpike and Infrastructure Commission (OTIC) slip repair project at milepost 132.6. This project included…
Project 188-19 Cameron WV When The Great Lakes Construction Co. was presented with this project in late spring 2019, the compounding challenges seemed nearly insurmountable.…
Project 151-19 Akron, OH The City of Akron continues major expansion of its Water Reclamation Facility (WRF), originally opened in 1928, to manage wet weather…
Project 206-19 Cleveland, OH This large structural steel project included the installation of a large and complicated belt-conveyor system with shuttle drives and chutes completing…
Project 156-19 Westlake, OH Replacement of the plant’s two existing sludge dewatering plate presses with two new screw presses for dewatering solids from the raw…
Project 188-19 Cameron, WV Scope of work included substation mass earthwork. Approximately 50,000 CY of rock was drilled and blasted to bring the pad to…
ODOT Project 44-17 Hamilton County, OH The I-75 project consisted of the demolition of four bridges and the construction of three new bridges, Glendale Milford,…
Although Saturday, October 13th was wet and chilly, approximately 38 Great Lakes employees were on the job ready to work before sunrise! This exciting Community…
Project 174-19 Cleveland, OH Scope of work included adding pile clusters at ArcelorMittal’s Railroad bridge. These piling clusters will protect the bridge piers from heavy…
Project 171-19 Cleveland, OH Great Lakes’ scope of work included sewer replacement, drilled foundations, setting of cooling tower and tower platform.