Mill Creek Expressway Phase 5B

ODOT Project 3000-20
Mill Creek Expressway Phase 5B
Cincinnati, OH

The Mill Creek Expressway Phase 5B Project is 22 months into a 49-month project with approximately 50 union employees and counting. The team is focused on completing 7 bridge deck pours by the end of the year across 4 bridges. Four of those pours are on the new 2,000-foot flyover bridge connecting I-75 SB to I-74 WB. With over 3 million pounds of structural steel to set, 20,000 SF of MSE wall to build, and 4,000 LF of barrier wall to pour by the end of 2023, the project remains in full force.