Mill Creek Expressway Phase 5B

ODOT Project 3000-20
Mill Creek Expressway Phase 5B
Cincinnati, OH

The Mill Creek Expressway Phase 5B Project is Great Lakes’ largest contract to date at $84.9M and is 14 months into a 49-month project. The design portion of the project and all work for the City of Cincinnati is complete. For the next three-months, Great Lakes will have over 60 union employees focused on completing 60,000 SF of retaining wall, two bridge widenings, and the substructure for Unit 1 of the 2,000’ flyover bridge.