{"id":8048,"date":"2023-11-01T14:58:37","date_gmt":"2023-11-01T18:58:37","guid":{"rendered":"https:\/\/greatlakesway.com\/?p=8048"},"modified":"2023-11-16T10:21:25","modified_gmt":"2023-11-16T15:21:25","slug":"cedar-point-sandusky-oh-phase-1-2-top-thrill-2","status":"publish","type":"post","link":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/","title":{"rendered":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2"},"content":{"rendered":"
\n
\n\t

Projects 455-23, 483-23, and 486-23
\nCedar Point, Phase 1 & 2 Project High Point<\/p>\n

Since 1870, Cedar Point has been a staple for summer fun and excitement for many families locally and nationally. What started out as a beach and bath house along the Lake Erie shoreline has turned into a mega-resort destination in Ohio.\u00a0<\/span><\/p>\n

In spring 2023, Cedar Point partnered with The Great Lakes Construction Co. for the installation of Top Thrill 2, the world\u2019s tallest and fastest triple-launch strata coaster. Great Lakes was awarded the initial contract for the Phase 1 Foundation Package. Phase 1 included installation of three 4\u2019 diameter X 60\u2019 deep drilled shafts below Lake Erie\u2019s water elevation, and a 5\u2019 reinforced concrete cap inside a permanent sheet pile cofferdam. Great Lakes installed two additional 4\u2019 diameter X 60\u2019 deep foundations north of this area. These foundations are the base of the 420\u2019 tall spike tower.\u00a0<\/span><\/p>\n

Throughout phase 1, Great Lakes worked with the owner through drawing changes, material fabrications, and schedule requirements. Our commitment to maintaining the schedule as well as our focus on keeping our work within the owner\u2019s budget was recognized. Meeting or exceeding the owner\u2019s expectations only reinforced their confidence in our work crews and project management capabilities.The relationship our team cultivated with Cedar Point \u2013 grounded in trust and mutual understanding, combined with our cost-effective approach \u2013 solidified their decision to engage us for additional work within the lagoon, and started the conversation to perform all civil work in its entirety for the Top Thrill 2.<\/p>\n

Cedar Point awarded Great Lakes with a Construction Manager\/GMP Contract for Phase 2 of the project. Phase 2 began in early summer 2023 \u2013 coinciding with Cedar Point\u2019s peak season and during park hours. Phase 2 includes the installation of additional ride foundations for the Brake Track, Launch Track, Fast Switch Track, Maintenance Track, and Ride Station. In addition to the foundation work, Great Lakes is responsible for the new Linear Synchronous Motor (LSM) Electrical Building and modifications to the new Maintenance Building, including all electrical and HVAC components. Next spring, Great Lakes will finish off the project completing the area development and site restoration package prior to opening in the Summer of 2024.\u00a0<\/span><\/p>\n

Watch\u00a0HERE<\/a> as\u00a0Zamperla<\/em>\u00a0and\u00a0Cedar Point<\/em>\u00a0debuted the groundbreaking Lightning\u00a0train\u00a0for\u00a0Top Thrill 2!<\/em><\/h4>\n<\/div>\n<\/div><\/div><\/div><\/div><\/div>","protected":false},"excerpt":{"rendered":"

Projects 455-23, 483-23, and 486-23 Cedar Point, Phase 1 & 2 Project High Point Since 1870, Cedar Point has been a staple for summer fun…<\/p>\n","protected":false},"author":255,"featured_media":8042,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[41],"tags":[],"cp_meta_data":{"_edit_last":["256"],"_thumbnail_id":["8042"],"_customify_content_layout":[""],"_customify_sidebar":[""],"_customify_disable_header":[""],"_customify_disable_page_title":[""],"_customify_disable_header_top":[""],"_customify_disable_header_main":[""],"_customify_disable_header_bottom":[""],"_customify_disable_footer_top":[""],"_customify_disable_footer_main":[""],"_customify_disable_footer_bottom":[""],"_customify_page_header_display":["default"],"_customify_page_header_title":[""],"_customify_page_header_tagline":[""],"_customify_page_header_image":["a:2:{s:2:\"id\";s:0:\"\";s:3:\"url\";s:0:\"\";}"],"_customify_page_header_shortcode":[""],"_customify_header_transparent_display":["default"],"_yoast_wpseo_content_score":["30"],"_yoast_wpseo_estimated-reading-time-minutes":["2"],"_yoast_wpseo_wordproof_timestamp":[""],"panels_data":["a:3:{s:7:\"widgets\";a:1:{i:0;a:9:{s:5:\"title\";s:0:\"\";s:4:\"text\";s:2840:\"

Projects 455-23, 483-23, and 486-23
\nCedar Point, Phase 1 & 2 Project High Point<\/p>\n

Since 1870, Cedar Point has been a staple for summer fun and excitement for many families locally and nationally. What started out as a beach and bath house along the Lake Erie shoreline has turned into a mega-resort destination in Ohio.\u00a0<\/span><\/p>\n

In spring 2023, Cedar Point partnered with The Great Lakes Construction Co. for the installation of Top Thrill 2, the world\u2019s tallest and fastest triple-launch strata coaster. Great Lakes was awarded the initial contract for the Phase 1 Foundation Package. Phase 1 included installation of three 4\u2019 diameter X 60\u2019 deep drilled shafts below Lake Erie\u2019s water elevation, and a 5\u2019 reinforced concrete cap inside a permanent sheet pile cofferdam. Great Lakes installed two additional 4\u2019 diameter X 60\u2019 deep foundations north of this area. These foundations are the base of the 420\u2019 tall spike tower.\u00a0<\/span><\/p>\n

Throughout phase 1, Great Lakes worked with the owner through drawing changes, material fabrications, and schedule requirements. Our commitment to maintaining the schedule as well as our focus on keeping our work within the owner\u2019s budget was recognized. Meeting or exceeding the owner\u2019s expectations only reinforced their confidence in our work crews and project management capabilities.The relationship our team cultivated with Cedar Point \u2013 grounded in trust and mutual understanding, combined with our cost-effective approach \u2013 solidified their decision to engage us for additional work within the lagoon, and started the conversation to perform all civil work in its entirety for the Top Thrill 2.<\/p>\n

Cedar Point awarded Great Lakes with a Construction Manager\/GMP Contract for Phase 2 of the project. Phase 2 began in early summer 2023 \u2013 coinciding with Cedar Point\u2019s peak season and during park hours. Phase 2 includes the installation of additional ride foundations for the Brake Track, Launch Track, Fast Switch Track, Maintenance Track, and Ride Station. In addition to the foundation work, Great Lakes is responsible for the new Linear Synchronous Motor (LSM) Electrical Building and modifications to the new Maintenance Building, including all electrical and HVAC components. Next spring, Great Lakes will finish off the project completing the area development and site restoration package prior to opening in the Summer of 2024.\u00a0<\/span><\/p>\n

Watch\u00a0HERE<\/a> as\u00a0Zamperla<\/em>\u00a0and\u00a0Cedar Point<\/em>\u00a0debuted the groundbreaking Lightning\u00a0train\u00a0for\u00a0Top Thrill 2!<\/em><\/h4>\n\";s:20:\"text_selected_editor\";s:7:\"tinymce\";s:5:\"autop\";b:1;s:12:\"_sow_form_id\";s:31:\"72955765265429b842fd43377602315\";s:19:\"_sow_form_timestamp\";s:13:\"1700148077645\";s:11:\"panels_info\";a:6:{s:5:\"class\";s:31:\"SiteOrigin_Widget_Editor_Widget\";s:4:\"grid\";i:0;s:4:\"cell\";i:0;s:2:\"id\";i:0;s:9:\"widget_id\";s:36:\"4f42bb77-4abe-422b-a10d-dfbeac0168c2\";s:5:\"style\";a:5:{s:27:\"background_image_attachment\";b:0;s:18:\"background_display\";s:4:\"tile\";s:21:\"background_image_size\";s:4:\"full\";s:24:\"background_image_opacity\";s:3:\"100\";s:16:\"border_thickness\";s:3:\"1px\";}}s:22:\"so_sidebar_emulator_id\";s:20:\"sow-editor-804810000\";s:11:\"option_name\";s:17:\"widget_sow-editor\";}}s:5:\"grids\";a:1:{i:0;a:2:{s:5:\"cells\";i:1;s:5:\"style\";a:5:{s:27:\"background_image_attachment\";b:0;s:18:\"background_display\";s:4:\"tile\";s:21:\"background_image_size\";s:4:\"full\";s:11:\"full_height\";s:0:\"\";s:14:\"cell_alignment\";s:10:\"flex-start\";}}}s:10:\"grid_cells\";a:1:{i:0;a:4:{s:4:\"grid\";i:0;s:5:\"index\";i:0;s:6:\"weight\";i:1;s:5:\"style\";a:0:{}}}}"],"_yoast_wpseo_primary_category":[""],"_edit_lock":["1700681787:256"]},"yoast_head":"\nCedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.<\/title>\n<meta name=\"description\" content=\"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.\" \/>\n<meta property=\"og:description\" content=\"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\" \/>\n<meta property=\"og:site_name\" content=\"The Great Lakes Construction Co.\" \/>\n<meta property=\"article:published_time\" content=\"2023-11-01T18:58:37+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2023-11-16T15:21:25+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp\" \/>\n\t<meta property=\"og:image:width\" content=\"1680\" \/>\n\t<meta property=\"og:image:height\" content=\"720\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/webp\" \/>\n<meta name=\"author\" content=\"1311-08192021-auth\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"1311-08192021-auth\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\"},\"author\":{\"name\":\"1311-08192021-auth\",\"@id\":\"https:\/\/greatlakesway.com\/#\/schema\/person\/d5bf92b1cfe0f09affd99b1889e42596\"},\"headline\":\"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2\",\"datePublished\":\"2023-11-01T18:58:37+00:00\",\"dateModified\":\"2023-11-16T15:21:25+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\"},\"wordCount\":376,\"publisher\":{\"@id\":\"https:\/\/greatlakesway.com\/#organization\"},\"image\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp\",\"articleSection\":[\"Industrial\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\",\"url\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\",\"name\":\"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.\",\"isPartOf\":{\"@id\":\"https:\/\/greatlakesway.com\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp\",\"datePublished\":\"2023-11-01T18:58:37+00:00\",\"dateModified\":\"2023-11-16T15:21:25+00:00\",\"description\":\"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.\",\"breadcrumb\":{\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage\",\"url\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp\",\"contentUrl\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp\",\"width\":1680,\"height\":720},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/greatlakesway.com\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/greatlakesway.com\/#website\",\"url\":\"https:\/\/greatlakesway.com\/\",\"name\":\"The Great Lakes Construction Co.\",\"description\":\"Safety. Quality. Efficiency.\",\"publisher\":{\"@id\":\"https:\/\/greatlakesway.com\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/greatlakesway.com\/?s={search_term_string}\"},\"query-input\":\"required name=search_term_string\"}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/greatlakesway.com\/#organization\",\"name\":\"The Great Lakes Construction Co.\",\"url\":\"https:\/\/greatlakesway.com\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/greatlakesway.com\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/2022-website-logo-header75-f-2.png\",\"contentUrl\":\"https:\/\/greatlakesway.com\/wp-content\/uploads\/2022-website-logo-header75-f-2.png\",\"width\":264,\"height\":139,\"caption\":\"The Great Lakes Construction Co.\"},\"image\":{\"@id\":\"https:\/\/greatlakesway.com\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.linkedin.com\/company\/the-great-lakes-construction-company\",\"https:\/\/www.youtube.com\/channel\/UCuMkB2P7RhBS47lTZKlNdkA\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/greatlakesway.com\/#\/schema\/person\/d5bf92b1cfe0f09affd99b1889e42596\",\"name\":\"1311-08192021-auth\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/greatlakesway.com\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/93082b52d3abc471be26f1232eadeeee?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/93082b52d3abc471be26f1232eadeeee?s=96&d=mm&r=g\",\"caption\":\"1311-08192021-auth\"},\"url\":\"https:\/\/greatlakesway.com\/author\/1311-08192021-auth\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.","description":"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/","og_locale":"en_US","og_type":"article","og_title":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.","og_description":"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.","og_url":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/","og_site_name":"The Great Lakes Construction Co.","article_published_time":"2023-11-01T18:58:37+00:00","article_modified_time":"2023-11-16T15:21:25+00:00","og_image":[{"width":1680,"height":720,"url":"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp","type":"image\/webp"}],"author":"1311-08192021-auth","twitter_card":"summary_large_image","twitter_misc":{"Written by":"1311-08192021-auth","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#article","isPartOf":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/"},"author":{"name":"1311-08192021-auth","@id":"https:\/\/greatlakesway.com\/#\/schema\/person\/d5bf92b1cfe0f09affd99b1889e42596"},"headline":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2","datePublished":"2023-11-01T18:58:37+00:00","dateModified":"2023-11-16T15:21:25+00:00","mainEntityOfPage":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/"},"wordCount":376,"publisher":{"@id":"https:\/\/greatlakesway.com\/#organization"},"image":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage"},"thumbnailUrl":"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp","articleSection":["Industrial"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/","url":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/","name":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2 - The Great Lakes Construction Co.","isPartOf":{"@id":"https:\/\/greatlakesway.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage"},"image":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage"},"thumbnailUrl":"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp","datePublished":"2023-11-01T18:58:37+00:00","dateModified":"2023-11-16T15:21:25+00:00","description":"The Great Lakes Construction Co. is a 100% employee-owned heavy civil construction company.","breadcrumb":{"@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#primaryimage","url":"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp","contentUrl":"https:\/\/greatlakesway.com\/wp-content\/uploads\/455-23-DJI_0657.webp","width":1680,"height":720},{"@type":"BreadcrumbList","@id":"https:\/\/greatlakesway.com\/cedar-point-sandusky-oh-phase-1-2-top-thrill-2\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/greatlakesway.com\/"},{"@type":"ListItem","position":2,"name":"Cedar Point, Sandusky, OH Phase 1 & 2 Top Thrill 2"}]},{"@type":"WebSite","@id":"https:\/\/greatlakesway.com\/#website","url":"https:\/\/greatlakesway.com\/","name":"The Great Lakes Construction Co.","description":"Safety. Quality. Efficiency.","publisher":{"@id":"https:\/\/greatlakesway.com\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/greatlakesway.com\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/greatlakesway.com\/#organization","name":"The Great Lakes Construction Co.","url":"https:\/\/greatlakesway.com\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/greatlakesway.com\/#\/schema\/logo\/image\/","url":"https:\/\/greatlakesway.com\/wp-content\/uploads\/2022-website-logo-header75-f-2.png","contentUrl":"https:\/\/greatlakesway.com\/wp-content\/uploads\/2022-website-logo-header75-f-2.png","width":264,"height":139,"caption":"The Great Lakes Construction Co."},"image":{"@id":"https:\/\/greatlakesway.com\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.linkedin.com\/company\/the-great-lakes-construction-company","https:\/\/www.youtube.com\/channel\/UCuMkB2P7RhBS47lTZKlNdkA"]},{"@type":"Person","@id":"https:\/\/greatlakesway.com\/#\/schema\/person\/d5bf92b1cfe0f09affd99b1889e42596","name":"1311-08192021-auth","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/greatlakesway.com\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/93082b52d3abc471be26f1232eadeeee?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/93082b52d3abc471be26f1232eadeeee?s=96&d=mm&r=g","caption":"1311-08192021-auth"},"url":"https:\/\/greatlakesway.com\/author\/1311-08192021-auth\/"}]}},"_links":{"self":[{"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/posts\/8048"}],"collection":[{"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/users\/255"}],"replies":[{"embeddable":true,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/comments?post=8048"}],"version-history":[{"count":3,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/posts\/8048\/revisions"}],"predecessor-version":[{"id":8070,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/posts\/8048\/revisions\/8070"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/media\/8042"}],"wp:attachment":[{"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/media?parent=8048"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/categories?post=8048"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/greatlakesway.com\/wp-json\/wp\/v2\/tags?post=8048"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}