Dayton Airport Terminal Apron Rehab, Phase 4

Project 396-22
Dayton Airport Terminal Apron Rehab, Phase 4
Dayton, OH

The Dayton Airport Terminal Apron Rehab, Phase 4 project is currently in its second construction season. This past season, Great Lakes removed approximately 40,000 SY of 16” concrete pavement and placed over 6,000 CY of new 16” pavement before the end of the year. The 2023 season is underway and the project is currently working on installing underground utilities. The project is currently on schedule to finish by the end of 2023.