Project 332-21 SBQ Facility Phase 1 Cuyahoga Heights, OH The majority of the site civil work has now been completed. Work transitioned to completing the…
Project 355-21 NEORSD Pearl & Jennings Storage Tanks & Pump Station Upgrade Cleveland, OH Excavation of the 50’ diameter, 120’ deep Jennings Road Storage Tank…
Project 392-22 Little Blue Run Capping Chester, WV The Little Blue Run 2022 Capping project was substantially completed at the end of September 2022. An…
ODOT Project 595-21 Bridge Rehabilitation Clark County, OH The Clark County Bridge Rehabilitation Project consisted of performing work on two bridges that were 22 miles…
ODOT Project 301-22 SR-3 Culvert Repair Medina, OH The SR-3 Culvert Repair Project consists of remediation of failing wingwalls for a culvert on SR-3 by…
Project 418-22 City of Lakewood Site Development Lakewood, OH In downtown Lakewood, the famous Facebook “Pit” is finally being developed. The site used to be…
Project 412-22 Great Lakes Brewing Co. Scranton Peninsula Cleveland, OH Remediation and site preparation got underway for the Great Lakes Brewing Co. Carter Road Project…
Project 357-21 Mentor Marsh Salt Fill Remediation Project Mentor, OH The Mentor Marsh is one of the largest natural marshes that remains along Lake Erie.…
Project 332-21 Cuyahoga Heights, OH Our Charter Steel SBQ Project continued working through the winter – completing all the underground utilities and placing concrete floor…
Project 354-21 Ashland County, OH The Great Lakes Construction Co. was awarded the Ashland Substation Project in October 2021. The entirely new substation will be…