Menu Close

NEORSD Easterly WWTP Aerated Grit

Project 707-13
Cleveland, OH

The Great Lakes Construction Co. demolished the existing Pre-Aeration Tank Building & Concrete Influent Line Structure, and constructed a new multistory facility. Principal features of the new facility include (4) four aerated grit tanks (25’w x 100’l x 30’h) , (2) two pump galleries (23’w x 100’l x 30’h), influent and effluent channels, new channels from the Headworks to a new junction chamber, 90” Hobas piping from JC to the new grit tanks, and a 16,250sf Grit Dewatering Building (2 story and basement), which houses the grit processing equipment and truck loading bays.